1. Contractor Delay

Unfortunately, our contractor won’t be able to begin work until Tuesday, August 19th. While we could seek alternatives, our current contractor consistently delivers high-quality work at 40–60% lower cost, making them the most cost-effective choice.

2. Full Lane Replacement Required

After a thorough review with the contractor, it’s confirmed that both lanes must be replaced due to extensive asphalt damage. We’ve contacted the county to validate this assessment.

3. Long-Term Improvements

On a positive note, all piping under the affected asphalt will be replaced, significantly reducing the risk of future leaks in that section for many years.

4. Cost-Saving Measures

We’ll also be installing additional piping during this project, which is expected to save over $200,000 in future expenses.

For more details, please attend the board meeting next Thursday, August 21st, where directors will ask questions and a deeper discussion will take place.

We’ll continue to provide updates as new information becomes available.